White Construction’s begins the sidewalk construction on 10/1/23. Weather permitting, the project’s schedule is as follows:
Week of 10/1/23: Maintenance of Traffic (throughout the project), Utility Locating, Tree Removal and Brush Cleaning, Infiltrative Trench Installation.
Week of 10/9/23: Infiltrative Trench Installation, Topsoil Stripping and Sidewalk Installation
Week of 10/15/23: Sidewalk Installation
Week of 10/22/23: Sidewalk Installation, Curb Ramp and Detectable Waring Surface Installation, Mulched Seeding and Crosswalk Thermoplastic Installation.
Week of 10/29/23: Project Cleanup and Completion.