Below is the update from our Town's Engineer: As of today, 4/29/24, Howard Companies has moved up their start date from May 8th to May 7th. Please see the …
[Read more...] about Update: 75th Street – Resurfacing Project – Moved up to May 7th
Indianapolis, IN
Below is the update from our Town's Engineer: As of today, 4/29/24, Howard Companies has moved up their start date from May 8th to May 7th. Please see the …
[Read more...] about Update: 75th Street – Resurfacing Project – Moved up to May 7th
Below is the update from our Town's Engineer: The 75th Street resurfacing project will be completed by Howard Companies. Howard Companies intends to start …
[Read more...] about 75th Street – Resurfacing Project – May 8th
Below is the update from our Town's Engineer: In preparation for the upcoming Pennsylvania Street Bridge Replacement being completed by the City of …
Indianapolis DPW has provided the Town of Meridian Hills with a tentative schedule for the upcoming Penn Street Bridge project. Please note that the City is …
White Construction's begins the sidewalk construction on 10/1/23. Weather permitting, the project's schedule is as follows: Week of 10/1/23: Maintenance of …
[Read more...] about 75th Street Sidewalk – Phase 2 – Project Schedule