Calumet is providing materials, services and installation of the Phase 1: 75th Street Sidewalk Project. Contractually, Calumet will be working on this project May 30th through July 31st. Crossroad Engineers will be providing bi-weekly summaries of work progress, a look ahead of what Calumet will be doing for the upcoming 2 weeks, and tracking work days and weather days throughout the project. Also, our July 11 Town Meeting will be providing a progress update.
July 15, 2022 Update:
From CrossRoad Engineers: Prior to July 11, construction was on hold due to an ongoing delay for an unmarked fiber optics line. Construction commenced on July 11. Two storm drain structures and 120ft storm pipe were installed. In addition, sidewalk prep began between Illinois St. and Meridian St. This included clearing of Right of Way and grading.
Thank you,
Colleen Field
Meridian Hills Town Councilor