“Smith Projects” was granted an extension of June 6th to complete the original Spring Road Work Project due to unseasonably cold temperatures, extensive rain and Covid-19 impacting crew members.
June 3 through June 6 – weather permitting
“Smith Projects” has provided the following schedule:
“Restoration at 80th Street and Williams Creek Drive is now completed. There are blankets at 80th due to slopes but Williams Creek was just seeded without blankets since it is so flat there.”
“The remaining crack seal on 75th Street is scheduled for Thursday and pavement markings for 75th and for Illinois Street is scheduled for Friday and Saturday if necessary.”